Imagine that you are a project manager for a construction company. You must create a WBS for the Site Preparation phase of this project. Here is a list of tasks.
| Task | Title | Predecessors | Duration |
| A | Contract Approval | — | 5 |
| B | Site Survey | A | 5 |
| C | Permit Application | A | 4 |
| D | Grading | B,C | 5 |
| E | Sewer Lines | B | 7 |
| F | Base Paving | D | 3 |
| G | City Approval | C,F | 6 |
| H | Final Paving | E,G | 8 |