Which activities would you focus on in order to get the project back on schedule

Project Management Assignment 4

All directions, lecture notes, and login and password to text book are in attachement.
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below and identify the critical path for the project. Can the project be completed in 40 weeks? Assume that Activity A actually finished at 3 weeks, Activity B actually finished at 12 weeks, and Activity C actually finished at 13 weeks. Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule